Road Work Week of June 14, 2021

On June 16, 17, and 18, 2021 the following portions roads will be reconstructed:

Talyor Road from Schools Road to the driveway at address # 35 Taylor Road, (Approximately 1400 ft) and Cemetery Road from Route 16 extending northerly to the driveway at #18 Cemetery Road (Approximately 600 ft).

The work will involve the reclamation of the existing pavement on June 16 and then re-grading the road cross-section on June 17 with repaving anticipated to occur on June 18. Motorists are requested to use alternative routes for June 16 through June 18, however the roads will remain open to one lane traffic flow during reclamation and regrading at speeds not to exceed 10 mph through the work zones. Motorists should expect to be driving upon gravel road base prior to the paving operation on June 18 th.  Detour routes may be posted should conditions warrant.